REVTERRA Dashboard

REVTERRA Engineering Dashboard

Sunday, April 26, 2026W17
Overall Progress
56%
Completed This Week
0
tasks done
In Progress
18
active tasks
Overdue
58
need attention
Team — Active Tasks
Narendra
  • S40MF-23 Thermal Analysis Overdue
  • S40MF-3 S40 Simulation Review Overdue
  • ITFB-39 Thermal Analysis Overdue
  • S40MF-25 Material Req. Analysis Overdue
  • S40MF-24 Windage Losses Overdue
  • S40MF-40 S40 Shaft Bolts - Torque Spec and Analysis Overdue
  • ITFB-24 Alternating stress analysis on the bolts holding the top shaft to the top disc of the stacked design Active
  • ITFB-36 Revalidate Torque Ramp Rate Overdue
+3 more
Gandhar
  • S40MF-9 Balancing Part Design Overdue
  • S40MF-26 Bearing Design Report Overdue
  • S40MF-30 Final Drawing Release Overdue
  • ITFB-40 Sensor Mounts Design Active
  • S40MF-4 S40 Drawing Release Overdue
  • ITFB-42 Bearing Design Report Active
  • ITFB-55 Velicon Mounting Part Design Active
  • ITFB-65 ITFB Physical Shaft Coupler Design Active
Curtis
  • S40MF-6 Material Procurement Overdue
  • S40MF-27 Parts Received QA Overdue
  • ITFB-54 Velicon Mounting Parts Fab Overdue
  • ITFB-47 Parts received QA Overdue
Satyam
  • S40MF-7 Balancing Shafts Fabrication Active
  • S40MF-8 Balancing Operation Overdue
  • ITFB-63 ITFB Ancillary Parts Fab Active
  • ITFB-64 ITFB Physical Shaft Coupler Parts Fab Overdue
  • ITFB-62 ITFB Motor Mount Fabrication Active
  • S40MF-13 High Torque Mag. Coupler Procurement Active
Zach
  • ITFB-29 Create drawing for ITF concrete pad, including anchors to bolt the ITF into, and including space for the Current Power enclosure to sit on Overdue
  • S40MF-16 Sensor Mounting Overdue
  • ITFB-69 Detailed Drawing of Embedded Plate and Concrete Pad Overdue
  • ITFB-52 Sensor Mounting Overdue
  • ITFB-49 Flywheel Assembly Overdue
  • ITFB-51 55kW-3600 RPM Motor Integration Overdue
  • S40MF-31 Induction Motor Integration for Mechanical Testing Overdue
  • ITFB-7 ITF Parts Received Overdue
+2 more
Ben
  • S40MF-22 System IO List Active
  • S40MF-12 High Torque Mag. Coupler Design Confirmation Active
  • S40MF-39 Document motor protection thresholds Overdue
  • CPSP-36 Follow up: Shipping carrier recommendations from Noah Active
  • ITFB-32 Share requirements with Skyworks and agree on timeline for site preparation Overdue
  • S40MF-37 Finalize skid layout dimensions Overdue
  • S40MF-38 Cable routing design (skid to flywheel) Overdue
  • CPSP-29 Follow up: Sine wave filter loss and voltage drop Active
+9 more
Attention Needed
S40MF-22 System IO List Ben Jawdat Overdue
S40MF-23 Thermal Analysis Narendra Gupta Overdue
S40MF-3 S40 Simulation Review Narendra Gupta Overdue
S40MF-12 High Torque Mag. Coupler Design Confirmation Ben Jawdat Overdue
Needs Scheduling (2)
CPSP-24 Pad Steel Fabrictaion Zach Galvarro
CPSP-25 Pad Concrete Pour Satyam Shukla